Show Treatment wall

Vertical wall repair
 
Basal wall repair
 
repointing (sq ft)
-  
masonry (sq ft)
-  
stone site (number)
-  
stone fresh (number)
-  
capping (linear feet)
-  
mortar (number of buckets)
-  
Comments

Side view of collapsed east wall.
Date work started: September 23, 1970 and date work finished: September 30, 1970.
Took 15 1/2 days to complete work.
Personnel on the job: Cecil Werito and 2 laborers.

 
Notes