Preservation Records

Year Site Room name

Story

Backfills Walls Crew
1999 Chetro Ketl 29SJ 1928 Room 1 1st Story Start: 2/1999, End: 2/1999 - -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 2 1st Story Start: 2/1999, End: 2/1999 - -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 3 1st Story Start: 2/1999, End: 5/1999, Drainage pipe installed. Drainage inlet located in center of room. - -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 4 1st Story Start: 2/1999, End: 5/1999, Drainage pipe installed. - -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 5 1st Story Start: 2/1999, End: 2/1999 - -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 114 1st Story Start: 2/1999, End: 5/1999, Drainage pipes installed. Drainage outlet located in center of room. - -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 32 1st Story Start: 2/1999, End: 2/1999 - -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Site Overview men at work 1st Story - None, Floor -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Site Overview Scaffolding / Trucks/Equip Bracing / Roofs / Set-up - ROOF, NW Quad, , … (9) -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 76 1st Story - North -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 105 1st Story - South -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 33 1st Story - South, North -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 73 1st Story - West, South, East, … (4) -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 81 1st Story - South, North -
Edit Delete Show Print
1999 Chetro Ketl 29SJ 1928 Room 85 1st Story - West, South, East, … (4) -