Wijiji 29SJ 577 Room: Room 52 Story: 1st Story Year 2003
Capping Mortars
# of buckets Source Material
Dirt Cans Cups of color
Sand Describe Color:
Clay Duraweld-C (1:4)
Cement Duraweld-C (other)
Comments:
Wall Mortar
# of buckets Source Material
Dirt Duraweld C (1:4)
Sand Duraweld (other)
Clay
Comments:
Walls recorded: North, East
Start: End: Person Days:
 
Overall Comments: Created for attaching photos. No documentation of work done. bg 10-7-10. Vertical and basal wall treatment was done to the wall. A treatment form was not really created and the crew used a map to indicate the work they done on a wall.



Wijiji 29SJ 577 Room: Room 52 Story: 1st Story Wall: North Interior Year 2003
Condition
Condition:
Mortar Erosion: Poor
Basal Erosion: Poor








Wijiji 29SJ 577 Room: Room 52 Story: 1st Story Wall: North Interior Year 2003
Treatment
Treatment:
Vertical Wall Repair:
Basal Wall Repair:
Repointing (sq ft): 7.0
Treatment comment: Information was not really entered on a documentation form yet and a map was created to document work done.








Wijiji 29SJ 577 Room: Room 52 Story: 1st Story Wall: East Interior Year 2003
Condition
Photo type: Before 97660
Image #: 097660
Catalog #:        Accession #:
Condition:
Loose wall caps: Poor
Stone Erosion: Poor
Mortar Erosion: Poor
Basal Erosion: Poor








Wijiji 29SJ 577 Room: Room 52 Story: 1st Story Wall: East Interior Year 2003
Treatment
Treatment:
Basal Wall Repair:
Repointing (sq ft): 3.0
Treatment comment: Information was not really entered on a documentation form yet and a map was created to document work done.