Chetro Ketl 29SJ 1928 Room: Room 23 Story: 1st Story Year 1993
Capping Mortars
# of buckets Source Material
Dirt Cans Cups of color
Sand Describe Color:
Clay Duraweld-C (1:4)
Cement Duraweld-C (other)
Comments:
Wall Mortar
# of buckets Source Material
4.0 Dirt Duraweld C (1:4)
2.0 Sand Duraweld (other)
1.0 Clay
Comments:
Walls recorded: South, West, North
Start: 28/9/1993 End: 29/9/1993 Person Days: 1.0
 
Overall Comments: Leo Chiquito worked in Room 23 on 8/31/93 to 9/17/93, 3 person days.



Chetro Ketl 29SJ 1928 Room: Room 23 Story: 1st Story Wall: South Interior Year 1993
Condition
Condition:
Mortar Erosion: Poor
Basal Erosion: Poor
Note:
     Loose/fallen chinking








Chetro Ketl 29SJ 1928 Room: Room 23 Story: 1st Story Wall: South Interior Year 1993
Treatment
Treatment:
Vertical Wall Repair:
Basal Wall Repair:
Repointing (sq ft): 90.0
Mortar (# buckets): 7.5








Chetro Ketl 29SJ 1928 Room: Room 23 Story: 1st Story Wall: West Interior Year 1993
Condition
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor
Basal Erosion: Poor
Note:
     Loose/ fallen chinking
Mortar Erosion: Poor
Basal Erosion: Poor
Note:
     Loose/fallen chinking








Chetro Ketl 29SJ 1928 Room: Room 23 Story: 1st Story Wall: West Interior Year 1993
Treatment
Treatment:
Vertical Wall Repair:
Basal Wall Repair:
Repointing (sq ft): 90.0
Mortar (# buckets): 7.5
Vertical Wall Repair:
Repointing (sq ft): 12.0
Stone replaced (#): 23.0
Mortar (# buckets): 2.0








Chetro Ketl 29SJ 1928 Room: Room 23 Story: 1st Story Wall: North Interior Year 1993
Condition
Condition:
Mortar Erosion: Poor
Basal Erosion: Poor
Note:
     Loose/ fallen chinking








Chetro Ketl 29SJ 1928 Room: Room 23 Story: 1st Story Wall: North Interior Year 1993
Treatment
Treatment:
Vertical Wall Repair:
Repointing (sq ft): 11.0
Stone replaced (#): 11.0
Mortar (# buckets): 1.5