New Alto 29SJ 388 Room: Room 10 Story: 1st Story Year 2003
Capping Mortars
# of buckets Source Material
Dirt Cans Cups of color
Sand Describe Color:
Clay Duraweld-C (1:4)
Cement Duraweld-C (other)
Comments:
Wall Mortar
# of buckets Source Material
3.0 BLM quarry Dirt Duraweld C (1:4)
1.0 Purchase Sand Duraweld (other)
Clay
Comments:
Walls recorded: West, East
Start: 24/7/2003 End: 24/7/2003 Person Days: 1.0
 
Overall Comments: Vertical is OK, only needs 1 big stone to replace and the rest of the walls are all right



New Alto 29SJ 388 Room: Room 10 Story: 1st Story Wall: West Interior Year 2003
Condition
Photo type: Before 94777
Image #: 094777
Catalog #:        Accession #:
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor
Basal Erosion: Poor








New Alto 29SJ 388 Room: Room 10 Story: 1st Story Wall: West Interior Year 2003
Condition
Photo type: Before 94778
Image #: 094778
Catalog #:        Accession #:
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor
Basal Erosion: Poor








New Alto 29SJ 388 Room: Room 10 Story: 1st Story Wall: West Interior Year 2003
Treatment
Photo type: After 94782
Image #: 094782
Catalog #:        Accession #:
Treatment:
Treatment comment: Repair included repointing, masonry, and mortar work. Repair of basal erosion and stone replacement was done where appropriate.








New Alto 29SJ 388 Room: Room 10 Story: 1st Story Wall: East Interior Year 2003
Condition
Photo type: Before 94775
Image #: 094775
Catalog #:        Accession #:
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor
Note:
     vertical wlls OK; need 1 stone replaced








New Alto 29SJ 388 Room: Room 10 Story: 1st Story Wall: East Interior Year 2003
Condition
Photo type: Before 94776
Image #: 094776
Catalog #:        Accession #:
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor
Note:
     vertical wlls OK; need 1 stone replaced








New Alto 29SJ 388 Room: Room 10 Story: 1st Story Wall: East Interior Year 2003
Treatment
Photo type: After 94783
Image #: 094783
Catalog #:        Accession #:
Treatment:
Repointing (sq ft): 0.75
Masonry: 0.75
Stone replaced (#): 3.0
Mortar (# buckets): 0.5