Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Year 2013
Capping Mortars
# of buckets Source Material
Dirt Cans Cups of color
Sand Describe Color:
Clay Duraweld-C (1:4)
Cement Duraweld-C (other)
Comments:
Wall Mortar
# of buckets Source Material
Dirt Duraweld C (1:4)
Sand Duraweld (other)
Clay
Comments:
Walls recorded: North, East, South, West
Start: 12/9/2013 End: 19/9/2013 Person Days: 4.0
 
Overall Comments: North wall is in good shape except just needs repointing with good mud at the top. East wall seems okay, just a few small stones needs replacement and good repointing with duraweld mortar. South wall almost the whole wall was really bad, especially in middle area the stones were really bad and loose old mortar and dirt, it needs good stones for replacement, remove old mortar and dirt, replaced good stones and repointed with good mud. West wall there were some bad stones, remove bad stone, old mortar, dirt clean it good and replaced good stones and stones reset, using fresh mud repointed where it needs repointing.



Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: North Interior Year 2013
Condition
Photo type: Before 118816
Image #: 118816
Catalog #:        Accession #: 880
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor








Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: North Interior Year 2013
Treatment
Photo type: After 118805
Image #: 118805
Catalog #:        Accession #: 880
Treatment:
Vertical Wall Repair:
Repointing (sq ft): 2.0
Masonry: 2.0
Stone replaced (#): 3.0
Mortar (# buckets): 1.5








Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: East Interior Year 2013
Condition
Photo type: Before 118818
Image #: 118818
Catalog #:        Accession #: 880
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor








Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: East Interior Year 2013
Treatment
Photo type: After 118806
Image #: 118806
Catalog #:        Accession #: 880
Treatment:
Vertical Wall Repair:
Repointing (sq ft): 3.0
Masonry: 3.0
Stone replaced (#): 7.0
Mortar (# buckets): 1.0








Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: South Interior Year 2013
Condition
Photo type: Before 118708
Image #: 118708
Catalog #:        Accession #: 880
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor








Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: South Interior Year 2013
Treatment
Photo type: After 118807
Image #: 118807
Catalog #:        Accession #: 880
Treatment:
Vertical Wall Repair:
Repointing (sq ft): 18.0
Masonry: 3.0
Stone replaced (#): 47.0
Mortar (# buckets): 7.0








Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: West Interior Year 2013
Condition
Photo type: Before 118709
Image #: 118709
Catalog #:        Accession #: 880
Condition:
Stone Erosion: Poor
Mortar Erosion: Poor








Pueblo del Arroyo & Tri-wall 29SJ 1947 Room: Room 144 Story: 3rd Story Wall: West Interior Year 2013
Treatment
Photo type: After 118808
Image #: 118808
Catalog #:        Accession #: 880
Treatment:
Vertical Wall Repair:
Repointing (sq ft): 6.0
Masonry: 2.0
Stone replaced (#): 9.0
Mortar (# buckets): 2.0