Kin Bineola Pinacle 29SJ 1578 Room: Room 1 Story: 1st Story Year 2006
Capping Mortars
# of buckets Source Material
2.0 Local source Dirt Cans Cups of color
1.0 Purchase Sand Describe Color:
Clay Duraweld-C (1:4)
Cement Duraweld-C (other)
Comments:
Wall Mortar
# of buckets Source Material
2.0 Local source Dirt Duraweld C (1:4)
1.0 Purchase Sand Duraweld (other)
Clay
Comments:
Walls recorded: West, East
Start: 5/4/2006 End: 11/4/2006 Person Days: 4.0
 
Overall Comments:



Kin Bineola Pinacle 29SJ 1578 Room: Room 1 Story: 1st Story Wall: West Exterior Year 2006
Condition
Photo type: Before 82469
Image #: 082469
Catalog #: 85198        Accession #: 803
Condition:
Loose wall caps: Poor
Mortar Erosion: Poor
Other Conditions:
     Mortar Erosion Poor
     Loose and cracked Wall Caps Poor








Kin Bineola Pinacle 29SJ 1578 Room: Room 1 Story: 1st Story Wall: West Exterior Year 2006
Treatment
Photo type: After 82479
Image #: 082479
Catalog #: 85198        Accession #: 803
Treatment:
Repointing (sq ft): 19.0
Stone replaced (#): 10.0
Capping: 23.0
Mortar (# buckets): 9.0
Treatment comment: Paul Tso, Leo Chiquito and James Yazzie all worked in this room.
Other Treatment:
     Replaced Mortar
     Repaired loose and cracked wall








Kin Bineola Pinacle 29SJ 1578 Room: Room 1 Story: 1st Story Wall: East Exterior Year 2006
Condition
Photo type: Before 82470
Image #: 082470
Catalog #: 85198        Accession #: 803
Condition:
Loose wall caps: Poor
Mortar Erosion: Poor
Other Conditions:
     Mortar Erosion Poor
     Loose and cracked Wall Caps Poor








Kin Bineola Pinacle 29SJ 1578 Room: Room 1 Story: 1st Story Wall: East Exterior Year 2006
Treatment
Photo type: After 82478
Image #: 082478
Catalog #: 85198        Accession #: 803
Treatment:
Repointing (sq ft): 27.0
Stone replaced (#): 10.0
Capping: 24.0
Mortar (# buckets): 12.0
Treatment comment: Paul Tso, Leo Chiquito and james Yazzie all worked in this room.
Other Treatment:
     Repaired loose and cracked wall
     Replaced Mortar